Cistern Update, May 7, 2024

(Notice posted on the bulletin board, 5-7-24, by HOA Board President, Hal Goldback):

As luck would have it, the delivery of the pumps has been delayed. It appears that municipalities and repeat buyers have outclassed our one-off order. While we anticipated delivery by April 30, delivery is now expected by May 30.


The wiring is in space and the control panel has been installed. If you see a crane at the site, you’ll know that installation is in process. As soon as the pumps are installed, backfill and final grade work will be completed. That will be followed by a complete fill of 45,000 gallons by Monument Fire and testing. Then, a demonstration will be performed by Monument Fire, for the benefit of our homeowners.